Maintenance
Asbestos Management Plan Notification
Iberville Parish School Board retained Wynn L. White Consulting Engineers, Inc. to inspect Iberville Parish School Board facilities for the presence of asbestos containing materials. The work consisted of evaluating asbestos containing materials identified during previous inspections, identifying materials suspected of containing asbestos, sampling those materials, analyzing the samples, making a hazard assessment, making recommendations, and preparing Asbestos Management Plans.
The asbestos management plans are on file at the facility and at the following location:
Wynn L. White Consulting Engineers, Inc.
P.O. Box 83527
Baton Rouge, LA 70884-3527
Phone: 225-761-9141 extension 2
Fax: 225-761-4450
Attn: Chris White, P.E.
Email: cwhite@wynnwhite.com
DISTRICT FACILITY PROJECT UPDATES
CRESCENT ELEMENTARY SCHOOL
Cafeteria Renovation
○ HVAC ducts have been installed $2,000,000
○ Lights are being installed
○ Ceiling grids install in the kitchen- 100%
○ Kitchen flooring installed- 95%
○ Cooler and freezer installation-100%
○ Fire alarm installation- 90%
○ Kitchen equipment installation- 01-06-25
○ Installation of new windows
■ Ordering – ETA 2 weeks
DORSEYVILLE ELEMENTARY SCHOOL
Cafetorium
○ Painting ongoing-60% $4,400,000
○ Installation of hard ceiling starts – 01-06-25
○ Kitchen Tile installed -100%
○ Installation of kitchen equipment starts- 01-08-25
○ Change order for new tank complex
■ Awaiting engineer drawing for underground piping- 100%
■ Starting overhead pipework- 80%
■ Fabrication of new tank- awaiting material
○ Lightning- 90%
○ Windows- 98%
○ Acoustical tile starts– 01-07-25
○ Sound system starts 01-13-25
○ Roll down screen starts- 01-13-25
EAST IBERVILLE ELEMENTARY/HIGH SCHOOL
Field House
○ Final Completion
■ ?? $3,800,000
IBERVILLE ELEMENTARY SCHOOL
HVAC heat exchanger replacement $50,000
○ Installation of new equipment- 100%
○ Start-up of new equipment- 100%
MSA-EAST ACADEMY
• Removal of garden structure
o Awaiting start time from Contractor
MSA-WEST ACADEMY
Gym Floor Repair
o The original contractor will make repairs
Using the 2.5” wide flooring $74,000
Pre-K Additional
○ Mobilized equipment – 100%
○ Ordered materials-100%
○ Started demo work for the new addition- 100%
○ Footing poured – 100%
○ Re-routed main water line- 100%
NORTH IBERVILLE ELEMENTARY/HIGH SCHOOL
Cafeteria Renovation
○ Overhead door installation - 100% $1,500,000
○ Starting punch list items 12-16-24
New Classroom Building G
○ Sites clean up – ongoing
○ CMU block- ongoing
○ MEP rough in opening thru CMU starts- 01-06-25
PLAQUEMINE HIGH SCHOOL
WHITE CASTLE HIGH SCHOOL
New Competition Gym
○ Perimeter fence to be installed - 100%
○ Punch list item- continue working $8,560,000
CENTRAL OFFICE COMPLEX
CIA HVAC System Upgrade
o Start date – TBD awaiting material to arrive
MULTI-CAMPUS
Press Box @ EIHS & WCHS
$600,000
EIHS-
■ Punchlist items – 90%
■ Completion date – 12/23/24
WCHS-
■ Punchlist items – 90%
■ Completion date – 12/23/24
FB Visitor RR/Concessions @ EIHS & WCHS
$800,000
WCHS-
■ Millwork to be installed – 100%
■ MEP trim-outs installed after millwork- 90%
■ Stainless steel countertops installed- 90%
■ Completion date – 1/14/25
EIHS-
■ Sheetrock installation- 90%
■ Epoxy floor installation – 100%
■ Stainless steel countertops installed- 1-08-25
■ Plumbing trim out- 1-13-25
■ Electrical Trim out- 1-15-25
■ Bathroom accessories- 1-20-25
■ Final grade and demobilize – 1-23-25
■ Completion date – 1/26/25