Iberville Parish School Board retained Wynn L. White Consulting Engineers, Inc. to inspect Iberville Parish School Board facilities for the presence of asbestos containing materials. The work consisted of evaluating asbestos containing materials identified during previous inspections, identifying materials suspected of containing asbestos, sampling those materials, analyzing the samples, making a hazard assessment, making recommendations, and preparing Asbestos Management Plans.
The asbestos management plans are on file at the facility and at the following location:
Wynn L. White Consulting Engineers, Inc.
P.O. Box 83527
Baton Rouge, LA 70884-3527
Phone: 225-761-9141 extension 2
Fax: 225-761-4450
Attn: Chris White, P.E.
Email: cwhite@wynnwhite.com
DISTRICT FACILITY PROJECT UPDATES
CRESCENT ELEMENTARY SCHOOL
Cafeteria Renovation
○ HVAC ducts have been installed $2,000,000
○ Lights are being installed
○ Paving Poured
○ Exterior wall Demoed
○ Walls framed in the kitchen
○ Pipe plumbing installation
○ Ceiling grids install
○ 1st cost of paint applied in cafeteria
DORSEYVILLE ELEMENTARY SCHOOL
Cafetorium
○ Painting ongoing-80% $4,400,000
○ Electrical to hook up soon
○ HVAC system start-up soon
○ Epoxy floor to start soon
○ Plumbing fixtures after epoxy
○ Kitchen Tile installed this week
○ Awaiting Change order for new tank complex
○ Flooring and all ceiling work will start as soon as the sprinkler system paperwork gets verified.
○ Awaiting a recommendation from Austin Fire on the new tank complex that is needed for this job.
EAST IBERVILLE ELEMENTARY/HIGH SCHOOL
Field House
○ Block and Brick installation continued $3,800,000
○ installing- 90%
○ Roofing begins 8-12-24
○ installing insulation panels-90%
○ Finishing East and south side paving-TBD
○ Electrical rough-in continues
○ 70% ○ Installing HVAC
○ ductwork 90% ○ Grading of site- TBD
○ Clean-up is ongoing ○ Substantial completion
○ TBD
IBERVILLE ELEMENTARY SCHOOL
HVAC heat exchanger replacement
○ Quotes have been verified $50,000
○ Material and equipment have been ordered
○ Estimate start time is Oct.28th
Hallway paint project
○ Project completed.
MSA-EAST ACADEMY
MSA-WEST ACADEMY
Gym Floor Repair
○ Waiting on confirmation and price of the correct material $80,000
Intercom System
○ Start date: 9-23-24 $400,000
○ Verifying all material and running wire
NORTH IBERVILLE ELEMENTARY/HIGH SCHOOL
Cafeteria Renovation
○ Walkway and awning in process $1,500,000
○ Installation completion 10/7-10/9
○ Clear anodized canopy installed
○ Flooring being installed
○ Walls framed ○ Drywall hung
○ Plumbing in walls has been insulated
○ Exhaust hood hung
○ Confirming delivery of SFS equipment Oct.
New Classroom Building G
○ Site work continues
○ Installed all underground drainage catch basin
○ Drove 3 test piles $400,000 $1,500,000
○ Will be driving more pile after test results are approved
○ Start planning and staging equipment for elevator construction
○ Muck out the side ditch for positive drainage
PLAQUEMINE HIGH SCHOOL
WHITE CASTLE HIGH SCHOOL
New Competition Gym
○ Gym floor is painted and sealed $8,560,000
○ Must stay off the floor for 2 weeks $8,560,000
○ Card readers have been installed
○ Terrazzo flooring is installed and polished
○ After the floor is ready we will hang scoreboards
CENTRAL OFFICE COMPLEX
MULTI-CAMPUS
Parking @ CES (Central Office, and Maintenance, removed from project)
○ Need to paint CMU walls and bollards $650,000
○ Substantial completion is given
Press Box @ EIHS & WCHS
$600,000
EIHS-
■ Awaiting on inspecting recommendations from Fire Marshall-100%
■ Working punch item list
■ Awaiting on structure steel by off from engineer
■ Substantial completion is given for occupancy
WCHS-
■ Awaiting on inspecting recommendations from Fire Marshall 100%
■ Working punch item list
■ Awaiting on structure steel by off from engineer
■ Substantial completion is given for occupancy
FB Visitor RR/Concessions @ EIHS & WCHS
$800,000
WCHS-
■ Site foundation grading in progress
■ Door and windows to be installed – 10-7-24
■ Sheetrock to start after windows and doors- 10-14-24
EIHS-
■ Poured concrete for foundation-100%
■ Metal building erection start date- 10-3-24
■ Interior frame starts date- 10-14-24